| Outdoor
Family Aquatic Center
Coon
Rapids, Iowa
Project
Manager:
Karla Engleen
Superintendent:
Judd Harmer
Architectural
Work:
Water Technology, Inc.
Contract
Amount:
$393,246.00
Completion
Date:
May 1998
Project Description:
The
City of
Coon Rapids
had a worn out old swimming pool
that was chewing a massive hole in the City budget due to the
extremely high cost of maintenance.
Rather than simply building a new pool, this progressive
community decided to construct a complete aquatic center, the
first of its kind in a several county area.
The pool features a full 6 lane, 25 yard competition area
with a diving well, a large zero depth entry wading area with
several water features, and a 30’ high tubular water slide.
In
addition to the pool, the complex features a bath house with
full restroom/changing rooms for both men and women, a large
well equipped concession stand, and an office area as well as
space for all of the mechanical equipment necessary to maintain
the pool. The well
planned layout allows patrons to walk directly through a
breezeway in the bathhouse controlled by coiling overhead doors
and onto the pool deck area or slip into one of the restrooms
directly adjacent to the breezeway.
A
large shade structure provides a cooler area adjacent to the
concession stand to help patrons cool off while enjoying a
snack. The
combination of grassy areas and vast amounts of pool deck space
help make sure the facility has something for everyone to enjoy
during their visit.
For
its part in the project, Shriver Construction Company served as
the General Contractor for the bathhouse which included the
construction of the bathhouse as well as the pool deck and site
fencing. Separate
prime contracts were issued by the City for construction of the
pool itself, the waterslide, mechanical work, and electrical
work.
Unusual or Unique Features:
As
the project was constructed by use of five separate prime
contractors, tremendous coordination was necessary to assure
that each contractor had their work completed in a sequence that
kept the project on schedule.
To further complicate this, the project was begun in late
fall and with a scheduled spring completion.
Failure to complete the project on this tight schedule
would leave the City without a pool until the final completion
date, which given the rather short outdoor pool season in West
Central Iowa would have been a financial burden on the City.
Construction
of the bathhouse was further complicated by a large underground
overflow tank that was built under the building.
The cast in place concrete tank required a large, deep
excavation and careful placement of reinforcing steel as well as
water stop material to prevent future leakage.
Finally the cast in place “lid” required extensive
shoring to hold the forms in place while the lid cured and
reached its full design strength.
Once the lid reached the required strength, the shoring
and forms had to be cut up and removed through the manhole
opening in the lid. All
of this concrete work forced the masonry bathhouse structure to
be constructed in the winter months entirely within heated
shelters creating an even greater need for careful coordination
among the various prime contractors.
Through
careful planning the project was successfully completed on
schedule thus allowing the City to open on time and enjoy a
complete initial season in its new facility.
|