| Denison
Job Corps Center Boeck
Building Dormitory Renovations
Denison, Iowa
Project
Manager:
Scott Shriver
Superintendent:
Ken Corbin
Architectural
Firm:
Kenneth Hahn Architects
Contract
Amount:
$2,390,305.00
Completion
Date:
April 2002
Project Description:
This
project was the culmination of a multi-year, multi-phase
renovation of an abandoned dormitory facility on the Denison Job
Corps campus. The
previous phases had involved the complete interior demolition of
the structure back to bare studs and joists. Additionally one of
the wings of the three wing building had been reconstructed in
other previous phases. Thus,
this project involved the reconstruction of the two remaining
wings.
The
building is shaped like a capital H with the south wing having
been previously finished and occupied by the owner.
The north wing was remodeled into dormitories on the 2nd
and 3rd floor with the main floor being converted
into spaces for job training programs conducted by the Center.
Also part of the project involved finishing the center
connecting section into a highly needed student center.
A
new stair was constructed in the middle of the dormitory wing to
provide better fire egress from the dormitory floors.
The existing fire stairs on each end of the dormitory
wing were removed and new stairs and railing installed.
Footings were also installed to allow for future
enclosure of these fire stairs by students in the Masonry trade
program conducted by the Center.
While
previous phases had “gutted” the building back to the studs
and joists, a great deal of demolition work was made necessary
to accommodate new openings for doors, windows, duct work, etc.
There were also large areas of the floor system that had
to have the joists removed and replaced or reinforced with
additional joists to properly handle the new loads from the
finished spaces above.
On
the main floor, a large commercial kitchen with an attached
dining area was constructed for the use of the Center’s highly
successful Food Preparation program.
In order to complete this portion of the work the
structure required many changes including the removal of load
bearing walls and replacement with steel beam and column
structures. Also
classroom and other instructional space was incorporated on this
floor for the use of the Center’s Security Services training
program.
The
new student center created on the second floor of the center
connecting section gave the Center some much needed space to
provide recreational and lounge space for its students.
The mixture of a large open space for games and
activities and some smaller, more comfortable spaces for
relaxation and conversation finally provided the Center with
some space to allow the students to better relax and interact
with each other.
The
top two floors were renovated into housing spaces for students.
Each floor has a complete laundry facility for the
students to use as well as a student lounge along with a
security office. Dormitory
rooms were constructed to house two students per room with a
shared bathroom between two rooms.
These tight quarter spaces required very careful
coordination to allow all trades access to complete their work.
The bathrooms were particularly tight making the
tolerances for measurements in these areas extremely critical to
maintaining a high quality finished product.
The end results were outstanding leading to a rather
short punch list and an extremely satisfied owner.
Unusual or Unique Features:
Through
careful scheduling, Shriver was able to develop a work plan that
allowed the building to be divided into several major sections,
and then allowing each major trade subcontractor to have access
to complete their portion of the work and move on to the next
section. This flow
plan took advantage of the repetitive tasks in the process
allowing the entire project to flow quickly and timely, while
maintaining a very high quality finished product.
Another
factor that complicated the entire project was that the brick façade
on the exterior of the building was not secured to the
structure. The
solution was to drill a series of specialized anchors into the
brick from the inside of the wall and then secure them to the
studs. This task had
to precede all finishes in all three levels of the building,
thus making it a critical item to timely completion.
Through careful planning, this work was completed in a
sequence that allowed a consistent work flow for all trades.
One
other factor that further complicated scheduling was that the
existing roof assembly had to be removed and replaced as well as
a great deal of the roof details reworked.
New mechanical units were installed on the roof which
kept the roof from being able to be reworked until a great deal
of the finish work was well underway inside.
This meant that very careful coordination was needed to
install the equipment and the new roof system while maintaining
a dry environment in the finished spaces.
Once again, the careful attention to scheduling
maintained by Shriver and its subcontractors made what could
have been a large problem into just another phase of the overall
project.
|