| Kuemper
Catholic High School
Gymnasium
and Fine Arts Renovation
Carroll, Iowa
Project
Manager:
Sam Harding
Superintendent:
Judd Harmer
Architectural
Firm:
OPN Architects, Inc.
Contract
Amount:
$1,561,370.00
Completion
Date:
February 1999
Project Description:
The
project consisted of an extensive renovation of the existing
gymnasium and fine arts areas as well as three small additions.
One addition houses the new wood shop area, thus allowing
the former wood shop to be renovated into a new vocal music room
complete with permanent risers.
The other two additions were constructed to create new
entry ways into the gymnasium with one serving as small
secondary entrance and storage area, while the other became the
new main entrance for both the gymnasium and the school itself.
Portions of the century old St. Angela’s wing were
renovated to provide additional classroom and rehearsal space
and a new instrumental music room.
A major window replacement project in this wing was also
completed on the multi-story structure.
The
heart of the project, however, was the gymnasium renovation.
The existing gym floor ran north/south with bleachers on
the west and a stage area on the east. The bleachers were removed including a series of rooms under
the permanent bleachers that housed the music department. On the other side of the gym, a series of scaffolding had to
be placed to support the existing roof structure in order to
allow for removal of the load-bearing wall between the gymnasium
and the stage. A
new truss was installed in place of the former load-bearing wall
to support the existing roof as well as the new roof over the
former stage area. Demolition
of the stage area and its roof area allowed the walls to be
extended to the full height of the gymnasium.
This new area allowed for construction of a locker room
facility at the gymnasium level with a balcony above on a new
precast spandeck structure.
A new wood floor system was installed running east/west
and new folding wood bleachers were installed on the north and
south as well as in the balcony, tripling the former seating
capacity to nearly 1500.
Unusual or Unique Features:
Removal
of the existing 36’0” high, 100’0” wide load bearing
12” concrete block wall and roof area over the former stage
was extremely complicated.
The existing gym roof had to be supported not only
against collapse but also against uplift from heavy winds for
the period of time that it would be open to the elements while
the new load bearing wall and truss structure was put in place.
Further complicating the process was the fact that the
existing floor structure of the former stage area, an area over
the former locker rooms,
was
too weak to allow for dropping large pieces of debris from the
demolition thus requiring the entire load bearing wall to be
taken down by hand in very small pieces.
Sequencing of this work was difficult because access to
the site was extremely limited.
The main power transformer for the entire facility as
well as adjacent elementary and middle schools was located on a
pole structure right next to the former stage area. With this high voltage area in immediate proximity, crane
access required very delicate maneuvering, which was the main
factor that drove the sequence of work.
Despite all of these challenges, all work on the gym was
completed between the end of the basketball season in the spring
of 1998 and the start of basketball season in the fall of 1998.
Another
part of the renovation included the addition of a long run of
custom fabricated display cases for trophies in the corridor
adjacent to the gymnasium.
These cases were painstakingly detailed to match an
existing display case that was to remain. This attention to detail was evidenced throughout the
project, but is probably most vividly displayed in the colors
and details that immediately strike you as you enter the new
gym.
|