| Madrid
Elementary School
1999
Addition and Remodeling
Madrid, Iowa
Project
Manager:
Scott Shriver
Superintendent:
Judd Harmer
Architectural
Firm:
Haila Engineering Group, Ltd.
Contract
Amount:
$1,961,074.00
Completion
Date:
September 2000
Project Description:
The
overall project was undertaken due to a fire that destroyed the
original 1915 wing of the school.
A bond issue was passed and, along with the insurance
proceeds, was used to raze the 1925 wing and provide funds for
the construction of new facilities onto the remaining portion of
the building. The
razing of the two structures left the existing building with
just two major levels and one small area on another level.
This
project consisted of demolition of part of the existing building
(not removed during main demolition to protect existing facility
against the elements), construction of two new wings and a
renovation of portions of the existing building.
One addition houses the new kindergarten classrooms,
while the other addition houses classrooms, a new lunchroom and
kitchen, new public restroom facilities, and a wheel chair lift
that makes the entire facility fully accessible. Portions of the existing building were renovated to provide a
new art room and special education rooms as well as numerous
fire code updates. New
windows were installed in most of the existing classrooms with
some windows requiring additional work to widen the openings for
egress windows. The
exterior of the existing gymnasium was given a facelift with a
new roof, new EIFS façade, and new windows.
The
heart of the project was the lunchroom with its large expanse of
glass and high ceilings giving it a very open feel.
A terrace area was located directly outside the lunchroom
windows with two sets of stairs leading to a new sidewalk along
the beautiful tree lined street.
Terrazzo flooring was installed in the lunchroom,
kitchen, corridors, and restrooms for long term maintenance and
beauty. The mixture
of brick masonry and split faced colored concrete block combined
to create a visually pleasing and impressive appearance to the
structure.
Unusual or Unique Features:
Removal
of the remaining portions of previously demolished building
wings was especially sensitive.
The existing stair tower had been left to prevent
flooding of the remaining building lower floor through the
stairs. Removal
required careful preparation to assure water tightness until the
new stair and roof assembly was in place.
The hallway adjacent to the existing cafeteria had also
been left to provide access for students to the cafeteria.
Removal necessitated providing alternate access to the
cafeteria along with careful removal of the hallway so as not to
effect the usage of the cafeteria.
Further
complicating the project at the onset was the fact that the
boiler for the entire building had previously been housed in the
now razed 1915 wing. A
new boiler had to be installed in a room under the existing
gymnasium and online for the 1999-2000 heating season.
All condensate piping throughout the building had to be
resloped to drain back to the new boiler, while all utilities
had to be rerouted and reinstalled to facilitate the change. An access hole had to be cut in the side of the foundation
wall to allow the new boiler to be installed.
Sequencing of this work was critical because access to
the area was limited and time was of the very essence.
|