|
United
Brick & Tile New Kiln
Building
Adel,
Iowa
Project
Manager:
Sam Harding
Superintendent:
John Zepp
Architectural
Work:
Design-Build by Shriver Construction Company
Structural
Engineering Firm:
Labate Engineering
Contract
Amount:
$1,057,909.00
Completion
Date:
September 2001
Project
Description:
When
Sioux City Brick & Tile Company needed to construct a new
multi-million dollar kiln building for its United Brick &
Tile Division in Adel, Iowa, it assembled the same team that had
successfully constructed the new kiln building for its Sergeant
Bluffs, Iowa plant in 1998 (a building that was listed in the
1998 VP Hall of Fame). That
team included Shriver Construction Company and VP Buildings
paired with Ceric, Inc., a world renowned kiln design and
manufacturing company.
This
building is significantly larger than the previous facility with
a capacity of 55 million brick per year.
It also incorporated a first of its kind, state of the
art robotic brick sorting and blending machine that totally
revolutionizes the way brick is packaged for shipment.
The entire process is highly automated utilizing state of
the art technologies that make the new plant one of the most
efficient in the world.
Shriver
Construction Company was responsible for the construction of the
foundation and the pre-engineered building shell.
The balance of the plant was constructed by Ceric, Inc.
as part of its kiln design package.
The plant was designed on a fast track basis which made
it necessary to order the building in phases.
Coordination between phases was critical as a common roof
plane was shared as well as tight tolerances at connections.
The building also had to be designed for expansion along
both sidewalls of the first phase as well as the entire endwall
of the second phase to accommodate a doubling of brick making
capacity to 110 million brick in the future.
The third phase, in fact, had to be redesigned just prior
to fabrication due to a late design change to add 14’0” of
additional height to fully cover taller clay storage bins and
still accommodate the clay conveyor system.
The additional height placed the final height of the
structure at 54’0” at the low sidewall with 45’0” rigid
frames. Two
additional small phases for a compressor room and additional
canopy space rounded out the five phase project.
A
Standing Seam roof system was chosen to provide premium
performance against the elements.
The Arctic White Panel Rib wall system provided an
attractive and economical covering for the exterior walls.
All walls were lined with 26 gauge liner to 7’4” to
protect the insulation system from damage.
Due
to the tremendous flexibility and unique design options
available from VP Buildings, Shriver Construction Company was
able to successfully construct a well designed building on a
very short timeline to meet and exceed the demands of its
customer.
Unusual
or Unique Features:
Since
the kiln design along with the accompanying machinery was still
largely in design stages when the building was ordered, a
tremendous amount of flexibility within the building design was
necessary to allow for potential changes as the kiln design was
completed. As noted
above, the choice of a pre-engineered building allowed the
flexibility to accommodate the last minute changes that came
about in the final kiln design stages.
Working
over the top of the kiln contractors presented a number of
challenges for safety requiring careful coordination and
communication. This
was further complicated by the language barriers between the
kiln designers (Ceric), a French company, the kiln contractors
from
Germany
, and Shriver Construction’s
forces. The teamwork
on the project, however, made this a fairly easy obstacle to
overcome.
Placement
of interior columns was complicated by the placement of
machinery as well as pits and rails upon which the kiln cars are
moved throughout the plant.
One machine, in particular, required a jack-beam system
to be installed in order to eliminate a column.
Many columns were spaced at varying intervals to maximize
the flexibility of design that allowed columns and foundations
systems to be placed in tight coordination with plant
operations. This
created a unique structure in which nearly no two frames had the
same interior column spacing.
It also required extremely close coordination between the
building foundations installed by Shriver Construction and the
various pits and machinery foundations in the plant.
Again the teamwork among all members of the project team
helped make this a well coordinated effort that kept the project
on track.
|