|
West
Central Cooperative
Flat
Grain Storage Building
Adair,
Iowa
Project
Manager:
Sam Harding
Superintendent:
John Zepp
Architectural
Work:
Design-Build by Shriver Construction Company
Contract
Amount:
$919,700.00
Completion
Date:
October 1997
Project
Description:
West
Central Cooperative needed to increase its grain storage
capacity at its facility in Adair.
Due to the nature of the site, construction space was
very limited. New
vertical storage units were possible, but nearly cost
prohibitive based on the poor soil conditions that required
extremely large, deep footings.
The cooperative had acquired a large metal building
across the creek from its facility and was using it to store
grain by trucking the grain to it and using a very labor
intensive operation to unload and pile it in the building.
By
examining the existing facility, Shriver Construction Company
was able to determine that the present building could be
disassembled and a new building installed using the same
foundation and floor. The
new building was designed with taller sidewalls and a higher
pitch allowing a grain conveyor to be hung down the center of
the building. West
Central then hired a millwright firm to construct a new conveyor
structure across the creek, connecting it to the building
conveyor. The
result was a much more useful facility that allowed the
cooperative to load the building with grain using automatic
conveying systems rather than the previous labor intensive
methods. The new
facility also holds more than twice as much grain through the
more efficient loading method and increased height of the
building.
All
in all, the new facility now holds 3.5 million bushels of corn
making it the largest flat storage building in the entire State
of Iowa. The building is covered with a Standing Seam Roof to provide
premium roof performance with ridge ventilators to evacuate the
grain dust and provide proper ventilation for the stored grain. The walls are Panel Rib with fiberglass wall lites to provide
some natural light to aid in the inspection of the grain.
Unusual
or Unique Features:
The
use of a new pre-engineered building structure on the foundation
system for a previous pre-engineered building required
tremendous coordination between Shriver Construction Company and
VP Buildings to ensure that the new building would both fit the
foundation and not overload the foundation at the same time.
Through careful measurement and verification, the new building
fit extremely well and was able to fall within the tolerances of
loads that the foundation was capable of supporting.
A
great deal of coordination was also required to assure that the
millwright firm hired by the owner was able to have adequate
clearances for its conveying equipment to operate.
This combined with working with them to coordinate the
entry point for the conveyor system and the connections entailed
by that also made excellent communication the key to the entire
project.
All
of this was further complicated by the need to coordinate with
contractor hired by the owner to dismantle the existing building
and remove it from the site.
Through careful coordination, the new building was able
to begin being erected while the old building was still being
removed, thus speeding up the entire construction cycle, a
critical item to the owner as the building was needed for grain
storage for the coming harvest.
The successful communication and coordination allowed the
owner to use the facility on time and within budget.
|